API RP 505 Vents, Relief Devices & Marine Terminal
Zone 0/1/2 extent-of-classification for process/instrument/tank vents, relief valves, and marine terminal berths (API RP 505, §8.2.3–8.2.4)
◉ API RP 505 §8.2.3–8.2.4 STYLE CHECK · NOT A REGULATORY SUBMISSION TOOL
⚠ Indicative tool only, and a companion to the existing API RP 505 calculators. The tank vent card below gives a more precise, localized breakdown (0.5m/1m/1.5m) than the Tank Area Classification calculator's Figure 6, which treats vents as part of a broader tank-level illustration — this is §8.2.3.3.1's own refinement, specific to atmospheric vents venting from a Zone 0 source, not a correction to the other tool. Verified directly against Figures 14–19 of this edition.
Identification
Research entries stay private to you for practice/testing. Switch to Official once this is a real design your company should see.
Vent / Relief Device Classification (§8.2.3)
Result
Zone Classification
Marine Terminal Handling Flammable Liquids (§8.2.4, Figure 19)
Berth area adjacent to tanker/barge cargo tanks. This is a fixed rule from the standard's own worked example, not a variable calculation — additional locations may need separate classification for other flammable-liquid sources on the berth, or per Coast Guard/other jurisdictional requirements (Note 3).
Result
ZONE 27.5m (25ft) horizontal, all directions on the pier side, from the portion of the hull containing cargo tanks
ZONE 27.5m (25ft) vertical, from water level to above the cargo tanks at their highest position
ZONE 1Open sump in deck for draining lines and hoses
Save & Report